GREENIDGE LAWSUIT DENIED: Judge deems approval process was ‘proper’

Acting State Supreme Court Justice William Kocher has dismissed a lawsuit brought by opponents over the reopening of the Greenidge Generation power plant on Seneca Lake.

Kocher heard oral arguments Jan. 24. His decision was dated April 21 and received by lawyers for both sides this week.

The seven-page decision states that the Sierra Club, the Committee to Preserve the Finger Lakes and president Peter Gamba and the Coalition to Protect New York and treasurer Kathryn Bartholomew have standing to bring the lawsuit.

They argued that the state Department of Environmental Conservation failed to conduct an adequate environmental review of the impacts of the project and its construction of a 4.6-mile gas pipeline from Milo to the station before issuing air permits.

FL Times:
Read More

Tweet about this on TwitterShare on FacebookShare on Google+Share on LinkedInPin on PinterestShare on RedditPrint this pageEmail this to someone

Also on FingerLakes1.com

  • Ⅾo ᶌᴑu wαnt tσ freеƖɑᴨce ೦v℮ᴦ ιnt℮rᴨeᴛ fr໐m ʏ੦υг ІᎥviᴨg rоoм Ꮷ೦іπg bαsiϲ ϳ૦Ꮟs οn уoυr сomputeᴦ foᴦ ƽeverɑI һ๐uᴦƽ eɑϲհ dɑყ‚ geᴛ pɑiᏧ $ȢƼ/h  anԁ get paid аt the ℮ᴨd ૦f eᴠ℮ry ԝeek vvhiןe cһ૦൦sing yοuг ѡork tim℮?Ꭾ?Tһеn vɪsit f௦l|oѡiռg liոᴋ foᴦ moᴦe infσ-⁃˗-˃ http://www.get.lc/41ttv

    dss